International & National Tender Support
Bid preparation for donor financed and government tenders. We build submissions to JICA, World Bank and ADB standards, and to the Public Procurement Rules 2025 through e-GP.
- JICA
- World Bank
- ADB
- e-GP and PPR 2025
A submission an evaluation committee can check line by line
Three financiers, three different ways of judging a bid
A submission assembled for one rulebook scores badly under another. Knowing which one applies is the first question we answer on any notice.
How the desk works
The three largest development financiers working in Bangladesh no longer judge a works bid the same way. Under JICA's Guidelines for Procurement under Japanese ODA Loans the contract goes to the lowest evaluated responsive bid, and a merit point system is not accepted in principle. The World Bank now requires rated criteria on most international competitive procurement, where the winner is the highest ranked bid rather than the cheapest. The Asian Development Bank went the same way for internationally advertised works from January 2026. A submission assembled for one of those rulebooks will score badly under another.
Our focus is the Japanese ODA loan package. Those works are tendered on JICA's own Standard Bidding Document for Works, normally single stage two envelope: the technical bid and the price bid are submitted together, the technical envelope is opened and assessed first, and only technically conforming bidders have their prices opened. We prepare both envelopes, keeping every price out of the technical one, because a price disclosed in the wrong envelope is a self inflicted disqualification.
That work is exacting in a particular way. The bid forms may not be altered and no blank may be left. Four documents are fatal if missing: the Letter of Technical Bid, the power of attorney, the bid security and the technical proposal. A specialised subcontractor named in the bid cannot be swapped after the deadline, and if that subcontractor fails the key activity test the bidder is disqualified, not just the subcontractor. Qualification is not compensatory either, so a strong experience record will not rescue a shortfall in financial capacity.
Domestically we work inside the Public Procurement Act 2006 and the Public Procurement Rules 2025, which replaced the 2008 rules in September 2025, submitting through e-GP under the Bangladesh Public Procurement Authority. Where a project is financed by a development partner, the financing agreement governs and the procuring entity issues a development partner variant of the standard tender document that names the financier and applies its anticorruption guidelines and sanctions. Knowing which of those frames applies is the first question we answer on any notice.
Before you commit to bidding
Most of the value sits before the work starts. A tender you should not enter is worth knowing about on day one, not in week three.
Go or no-go assessment
Which rulebook governs the notice, what the award actually turns on, and whether the package suits the firm at all.
Eligibility screen
Eligible source countries under the loan agreement, debarment and conflict of interest, and the one bid per bidder rule.
Qualification gap analysis
Each financial and experience criterion tested against the firm's real position. Qualification is not compensatory, so a gap in one area is not offset by strength elsewhere.
Joint venture strategy
Which criteria a joint venture can meet by summation, which the lead partner must carry alone, and what the agreement has to say.
Deadline feasibility
The advertised window against bank lead time for the bid security, site visit dates and the clarification cut-off. We say plainly if it is not enough.
Bonding and security capacity
The likely bid security, its validity tail, acceptable instruments and whether the firm's banking arrangements can carry it.
What the work covers, phase by phase
A bid goes through five phases. Choose one to see what the desk does at that point.
Read and decide
Before any cost is spent, the notice is read against the firm.
The instructions to bidders, conditions of contract and evaluation criteria read into a clause by clause checklist, so every required document, declaration and specification response is tracked to submission.
Eligible source countries, debarment and conflict of interest checks, then each financial and experience criterion tested against the firm's actual position before any decision to bid.
Measure and price
Quantities checked, then every rate built so its basis can be shown.
Measurement from drawings and specifications, reconciled against the issued bill of quantities, to the measurement convention the tender requires.
Every item priced from materials, labour, plant, overhead and profit, so the basis of a rate can be shown if the evaluation committee asks. Unpriced items are deemed covered and go unpaid, so nothing is left blank.
Write the proposal
The technical case, written against the evaluation criteria.
Method statement, construction programme, mobilisation schedule and site organisation, written against the evaluation criteria rather than as a generic narrative.
Personnel forms and CVs matched line by line to the required years in similar positions, and the equipment schedule with evidence of access. Alternative candidates are not evaluated, so each position is named once.
The health and safety plan and environmental plan the bid calls for, including the JICA Standard Safety Specification declaration and a named health and safety manager among the key positions.
Secure and assemble
Security, partners and the paperwork that makes a bid valid.
Instrument form, correct beneficiary, correct naming for a joint venture, and validity running past bid validity, arranged with the bank in time for the deadline.
Which criteria a joint venture may meet by summation and which the lead partner must carry alone, with the agreement, powers of attorney and partner information forms.
Submit and follow through
On time, in the right format, and answered after opening.
Upload through the portal with file sizes and transmission time allowed for, readable files, and the digital signature applied. The system accepts no late submission and permits no withdrawal after the deadline.
Responses that clarify without altering substance or price, arithmetic corrections accepted within time, bid validity extensions handled, and a debrief requested after award.
Submission under e-GP and on foreign aided projects
Domestic depth alongside the international work. Both routes run through this desk.
Have a notice closing soon?
Send the tender document and the drawings. We will tell you which rulebook governs it, what qualification it demands, and whether the deadline is realistic.
- JICA, World Bank and ADB bidding documents
- e-GP submissions under PPR 2025
- A go or no-go view before you spend